The summary's Forecast table shows, by section: Running, Actual, Open POs, EAC and EAC − Bid, with a job total including fee and insurance.
EAC is Running, plus any line where what is paid and still open on POs already exceeds its running figure (with that line's fringes). Fee and insurance are not added to an overrun.
Lines where actual plus open POs is more than running are flagged in the grid. Add the forecast to a PDF with Add forecast (open POs and EAC), or the Cost report preset.